CAP1915 Asphalt Resurfacing
Contractor: AJAX Paving Industries Inc
The week of May 27th, the contractor plans to mill the existing road surface of the Phase 1 streets, likely towards the end of the week, weather permitting.
The contractor also plans to begin concrete work on the Phase 2 streets, beginning on Fernwood Road, Lockwood Road and Woodcrest Drive. The contractor will work on the east side of the roadways first and any residents who will lose driveway access will be notified via door hanger in advance.