Link to 2025 Projects Map

2025 Construction Projects

The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project.

Click the map image above to view our new interactive project map to see if a project is affecting your street. To view the classic PDF version, click here.

Notices of Construction are mailed to affected residents and copies are available online here.

CAP2507 N. Main Street and Coolidge Highway Resurfacing

Coolidge Highway from 14 Mile Road to north city limits

N. Main Street from 13 Mile Road to north city limits


On Coolidge, the contractor will be paving the final layer of asphalt on the outside lanes, beginning on Tuesday. Then they will switch traffic and pave the inside lanes. Pavement striping to follow. Once complete, the road will be fully re-opened and crews will start removing the traffic control devices by the end of the week.

On Main Street, the contractor has finished paving and will be installing the new pavement striping mid-week. Once complete they will fully re-open the roadway and begin cleanup and removal of all the traffic control devices.

CAP2510 Water Main Improvements

1. Lexington Boulevard - N. Washington to Marais

2. Nakota Road - Crooks to Hillcrest/Massoit

3. E. Parent Avenue - Longfellow to dead end


The contractor is continuing to excavate and lay new piping this week working east to west on Lexington Boulevard.

CAP2535 Road Reconstruction

Ravena Avenue - Hillside Drive - Benjamin Traffic Circles

The contractor plans to finish joint sealing this week, followed by signage and paint markings.

2025 Sidewalk Program

The contractor is working on sidewalk replacement along the major roads in the target area and expects to complete the work by mid-August. Once the regular sidewalk work is complete the contractor will work on their punch list of repairs.

BEGINNING IN AUGUST:

CAP2506 13 Mile Road Resurfacing

Rochester Road to Campbell Road

This project is scheduled to begin the first week of August. Construction Notices have been mailed to property owners, residents and businesses along this section of 13 Mile Road. One lane will be open in each direction throughout construction and access to businesses will be maintained.

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2025 project map, find copies of mailed construction notices, and read about the city's various construction projects.