CAP2410 Water Main Improvements
All water main installation and connections are complete for both streets, only roadwork is remaining.
On Northwood, the contractor is doing concrete curbing and approaches near Woodward and Roseland this week. The contractor has also started paving the first layer of asphalt in sections east of the rail road tracks.
On Sycamore, the contractor has poured the new curb and gutter on the south side and is working on pouring south side approaches this week. Once poured the concrete will cure for 7-10 days before driveways can be re-opened to vehicles.
If residents driveway access will be affected, they will be notified beforehand via doorhanger.