CAP2405 Concrete Street Repairs
This project will replace some of the worst panels on the project streets shown in light blue on the project map linked above.
Phase 1, 2 and 3 streets are now complete.
For Phase 4 streets, the contractor will be working on second halves this week.
For Phase 5 streets, the contractor will be working on removing and pouring the first halves. Cement will be poured this week on Manitou and Windemere, then Marais.
First halves / Second halves - The contractor will work on one side of the street at a time to maintain access for residents during construction.