CAP2415/2416 Asphalt Resurfacing
This project will resurface several streets in the residential neighborhoods and the downtown.
CAP2416 Downtown
This week the contractor is finishing up concrete work on the project streets. Pavement milling on the downtown streets is tentatively scheduled for Thursday April 18th and Friday April 19th, weather permitting.
The first layer of new asphalt is tentatively scheduled to be placed the following week on Monday April 22nd and Tuesday April 23rd, weather permitting.
Any inclement weather may cause this work to be rescheduled.
CAP2415 Neighborhoods
New storm sewer installation will be performed on Irving this week in advance of road work.
On S. Pleasant, new concrete curbing and approaches are being installed on the east side of the roadway working north from Lincoln to 11 Mile, this will take most of the week.
The contractor will also continue with saw-cutting and curb removals on W. Sixth, W. Ninth and Maple Court this week.
The map below shows the downtown streets to be resurfaced and the table lists all the project streets and phases. The full project map linked above shows the project streets in orange and purple.