Improving Royal Oak
2023 project map

2023 Construction Project Map available now!

Use the map above to see if a project is affecting your street. The city realizes construction will be an inconvenience and all efforts to expedite the work will be utilized to minimize traffic conflicts and access to various properties abutting the project.

Notices of Construction have been mailed to affected residents and copies are available online here.

CAP2306 Rochester Road

This week the contractor will be continuing work on installing driveway approaches and intersections on the west side of the roadway, and also backfilling behind the new curbing.

Turn Restrictions and Closures:

Left turns will not be allowed for northbound and southbound traffic at 12 Mile Road, Girard Avenue and at 13 Mile Road during construction to avoid backups. Northbound Rochester Road will be completely closed between Gardenia Avenue and Dewey Street. Local access to the Oakview Cemetery and Rite Aid will remain open.

More information about the lane conversion can be found at:
www.romi.gov/RochesterRoad

CAP2308 Major Road Improvements

Vinsetta Boulevard and Lincoln Avenue:

The contractor has completed paving and only minor landscaping work is remaining on these two streets. The contractor is finishing up lawn restoration as the weather cools down.

Normandy Road:

The contractor is installing curbing and sidewalk along the south side of the roadway working west to east. Another crew will start on the north side working east to west. Limited traffic can enter Normandy Road at Coolidge Highway to access the businesses on Normandy Road, Normandy Court and Edgeland. The roadway will be closed at Delemere while the contractor completes the roadwork.

Normandy Road will be closed to thru traffic throughout construction. Residents with driveways on Normandy will still be able to enter the construction zone via the side streets to access their property. Businesses should direct their patrons, employees and deliveries to use Coolidge to access Normandy Road to minimize conflicts with construction work.

CAP2305 Concrete Repair Program

Concrete work is substantially complete on this project. Only minor landscape restoration work remains.

The contractor is also re-scheduling crews to begin the speed hump installation on Buckingham.

  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink

CAP2310 Water Main Improvements

Longfellow

This week the contractor will be working on landscape restoration and sprinkler repairs.

Sixth Street

The contractor is finishing up concrete work this week.

Houstonia

The contractor will start water main installation this week, beginning at Beechwood and working east.

  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink

CAP2315 Asphalt Resurfacing

The project streets shown in purple on the project map have been divided into three phases as shown below.

Phase 1

These streets are substantially complete. The contract has some minor landscape restoration and sprinkler repairs on their punch list to come back and finish.

Phase 2

On Phase 2 streets, the contractor will finish paving operations on Wednesday for Hoffman, with lawn restoration to follow after the holiday.

Phase 3

On Phase 3 streets, the contractor will be paving the roadway on Wednesday and Thursday this week, weather permitting.

CAP2315 Phasing
  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink

CAP2335 Road Reconstruction

Parkdale (Rochester to Ardmore)

The contractor has poured the new driveway approaches on the east half of the roadway and reopened the road to local traffic. Minimal work will be performed this week leading into the holiday. Driveways will remain closed until the concrete gains enough strength to take the weight of vehicles again.

Helene

The contractor has completed the remaining concrete work and will work on joint sealing and lawn restoration this week.

Brockton

Minimal work will be performed this week leading up to the holiday weekend. Next week the contractor will finish up the remaining driveway approach and sidewalks.

Parking: The school is allowing residents to use the parking lot off Brockton during construction. Some spaces will be marked for school use only but the remaining spaces are available to residents to park during construction.

Seventh

Minimal work, besides cleanup, will be performed on the block this week leading up to the holiday weekend. Next week the contractor will finish the remaining driveways and sidewalk ramps.

Ferris

The contractor will reopen the driveways and sidewalks that were poured last week once the concrete gains enough strength. Minimal work will be performed this week leading up to holiday weekend.

CAP2335 street list
  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink

CAP2302 Sidewalk Program

The contractor has completed the main sidewalk production work. The contractor will return in a few weeks to finish the remaining repairs and landscaping.

picture showing target area for 2023
  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink

RCOC Roundabout
Greenfield & Normandy 

The Road Commission for Oakland County (RCOC) has begun the installation of a roundabout at the intersection of Greenfield Road and Normandy Road. The intersection is closed to traffic for the duration of construction.

Side streets are closed at Greenfield near Normandy Road to help reduce cut-thru traffic.

If you have questions or concerns about the project, please contact the RCOC at 877.858.4804 or via email at dcsmail@rcoc.org

View the construction flyer

Please note that construction schedules are tentative, and may change based on weather delays, subcontractors or substantial field modifications. These updates are based on the information currently available.

You can visit www.romi.gov/currentprojects to view the 2023 project map, find copies of mailed construction notices, and read about the city's various construction projects.

Copyright 2023 Royal Oak. All Rights Reserved.
203 S Troy Street, Royal Oak, Michigan 48067

Powered by
CivicSend - A product of CivicPlus