CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
LANDSCAPE/LAWN RESTORATION: Lawn restoration is being delayed until end of August for more favorable temperatures for seeding.
Phase 1
Landscape restoration that didn't take or has not been completed will be delayed until Labor Day for more favorable weather.
Phase 2
For Delemere, the contractor plans to finish some remaining painting work this week.
Phase 3
Troy, University, Fairgrove, Pingree and Alexander - Asphalt paving is tentatively scheduled for Wednesday through Friday/Saturday this week.
Amelia - The contractors plans to mill the existing pavement on the block between Blair and Campbell this week, then work on road base repairs for both blocks. The gas company is also working on replacing sidewalks that were removed or damaged from the gas infrastructure work on this street.
Connecticut - The contractor will continue removal & replacement of concrete curbing and driveways this week. The gas company is also working on replacing sidewalks that were removed or damaged from the gas infrastructure work on this street.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.