CAP2215 Asphalt Resurfacing
Contractor: Hutch Paving, Inc.
LANDSCAPE/LAWN RESTORATION: Lawn restoration is being delayed until end of August for more favorable temperatures for seeding.
Phase 1
All the project streets in Phase 1 are complete, with minor restoration work remaining.
Phase 2
For Delemere, the contractor plans to work on restoration this week. They will also schedule the new pavement markings to be placed.
Phase 3
Troy, University, Fairgrove, Pingree an Alexander - Asphalt milling is scheduled to begin the week of the 11th. Once the streets have been milled, the contractor will begin work on adjusting the manhole structures for the final height of the roadway.
Amelia - The contractor is working on curbing and driveway approaches this week between Rochester and Blair. The gas company plans to finish their work this week between Blair and Campbell, so that the city's contractor can begin roadwork starting the week of the 11th.
Connecticut - The contractor will begin staking for the new curbing later this week with curb work scheduled to start the week of the 11th.
Temporary 'No Parking' signs will be placed where room for construction equipment is needed.